Recent work and projects yet to come
27. 4. 2023
Completed work at the time of inspection included installation of sewerage and stormwater systems, removal of excess soil and plowing, construction of bypass. The work, which is still ongoing, includes the excavation and gradual filling of the sewage, rain and water system, as well as the regular cleaning of Letkovská and Novoveská Streets. Planned future works include the construction of a retaining wall on Letkovská Street and the relocation of overhead power lines.